MBTA Operations Control Center
Boston, MA
- MBTA relocated Operation Control Center to Cabot Yard while renovation took place.
- Renovation encompassed the 7th and 8th floors.
- Highly secured area.
- Complex accelerated schedule-10 weeks to procure, 10 weeks to complete construction.
- All schedule obligations completed on time.
- 24 hour/ 7 day per week schedule.
- Complex logistics for deliveries and construction hours.
- OCC tracks and maintains the MBTA rapid transit and over 10,000 cameras on the railroads and roadways of the Commonwealth of Massachusetts.